Announcement - Investment plans for 2006 - 2009

UNIPETROL, a.s. evaluated it´s investment plans for years 2006 - 2009

CAPEX – according to years (in bn CZK)

 

2006

2007

2008

2009

Celkem

4,9

5,9

3,7

2,6

17,1

 

 

CAPEX – according to segments (in bn CZK)

 

Refining

Petrochemicals

Chemicals

Retail

Celkem

6,4

8,2

1,4

1,1

17,1

1. Before their implementation starts, investment projects included in the plan will be subject to further detailed analyses in terms of  their effectiveness, which may impact their amounts.

2. The above mentioned data do not include possible investment costs relating to the revamp of Česká rafinérská, a.s. facilities aimed at increasing the high-sulphur crude processing capacity. Possible alternatives of such revamp have been analyzed.